Plans for WtE plant in Delhi

Plans for WtE plant in Delhi

Timarpur Okhla Waste Management Company Ltd (TOWMCL) has submitted an application for approval of its proposed WtE project. The project involves the construction of a 17 MW WtE plant in Delhi, even though an exact…

Waste to Energy
Chennai tenders Kodungaiyur Waste to Energy project

Chennai tenders Kodungaiyur Waste to Energy project

The Greater Chennai Corporation has reportedly launched the tender for its WtE project in Kodungaiyur, Chennai. The future plant should process 2,100 tonnes (tpd as ecoprog understands) and generate 21 MW. In March 2024, it…

Waste to Energy
Test runs at Bidadi WtE plant to start soon

Test runs at Bidadi WtE plant to start soon

According to recent sources, the WtE plant in Bidadi, Karnataka, has been completed through a collaboration between the Karnataka Power Corporation Ltd (KPCL) and the Bruhat Bengaluru Mahanagara Palike (BBMP). According to the source, the…

Waste to Energy
Contract awarded for Ahmedabad WtE plant

Contract awarded for Ahmedabad WtE plant

Steamhouse India Limited has been awarded the contract for the design, engineering, construction, commissioning, operation, and maintenance of a WtE plant in Ahmedabad, Gujarat. The plant is to process 300 tpd of MSW and should…

Waste to Energy
MSW plant set up by Abu Road Brahma Kumaris Institute

MSW plant set up by Abu Road Brahma Kumaris Institute

The Abu Road Brahma Kumaris Institute has established an MSW processing Waste to Energy plant. Several campuses of the institute, including, amongst others, Shantivan, Anand Sarovar, and Manmohinivan, are used to gather the MSW. The…

Waste to Energy
Update on GCC’s Waste to Energy project

Update on GCC’s Waste to Energy project

The Greater Chennai Corporation’s (GCC) project to construct a WtE plant in Kodungaiyur, Chennai, under a PPP model is expected to be commissioned in 2 years. According to earlier sources, the plant is to process…

Waste to Energy
Bidadi WtE plant not yet operational

Bidadi WtE plant not yet operational

According to a new source, Karnataka Power Corporation Limited’s (KPCL) WtE facility in Bidadi, Karnataka, is not yet operational. According to September 2023 information, the plant was scheduled to start operations within the 2 to…

Waste to Energy
Deonar WtE project now scheduled for 2026

Deonar WtE project now scheduled for 2026

According to a new report, 10% of the Deonar WtE project that is currently under development in Mumbai, Maharashtra, have been completed, and a deadline for making the plant operational is targeted for 2026. This…

Waste to Energy
Bengaluru cancels four out of five WtE projects

Bengaluru cancels four out of five WtE projects

The state government of Bengaluru has reportedly decided to terminate four out of five WtE projects in Bengaluru. As further stated in the given source, the reason behind this decision is non-compliance with deadlines. The…

Temp
Proposal: SPV to purchase electricity from WtE plants

Proposal: SPV to purchase electricity from WtE plants

The Parliamentary Standing Committee on Energy has proposed to set up a special purpose vehicle (SPV) to purchase electricity from WtE plants and resell this power to interested entities. The SVP should include the Solar…

Waste to Energy
No progress on Galand WtE project

No progress on Galand WtE project

According to a recent source, the WtE project in Galand village in Ghaziabad, Uttar Pradesh, has not progressed so far. According to information from May 2023, at that time, a boundary was to be erected…

Waste to Energy
New plasma gasifier discussed in Margao

New plasma gasifier discussed in Margao

The Margao Municipality, Goa, is reportedly considering setting up a plasma gasification plant at the Sonsodo landfill for regional waste management. According to the Municipality, there will now be studies conducted as to whether the…

Waste to Energy
Update on Narela-Bawana WtE project

Update on Narela-Bawana WtE project

The Municipal Corporation of Delhi (MCD) is moving forward with its WtE project in Narela-Bawana. To implement the project, the MCD has concluded an agreement with the Power Grid Corporation of India concerning the relocation…

Waste to Energy
Moshi WtE plant started commercial production

Moshi WtE plant started commercial production

India-based Antony Waste Handling Cell Ltd has started commercial power sale from the Moshi WtE plant in Pune, Maharashtra, which was opened in August 2023. This is according to a recent news report. The plant…

Waste to Energy
Bengaluru plans to relocate all waste processing plants

Bengaluru plans to relocate all waste processing plants

The Government of Bengaluru, Karnataka, has announced plans to relocate all waste processing plants to uninhabited areas outside the city. According to the announcement, the plan is to set up so-called “Integrated Solid Waste Management…

Waste to Energy
Bidadi WtE plant to open soon

Bidadi WtE plant to open soon

The proposed WtE plant in Bidadi, Karnataka, is expected to be operational within the next 2 to 3 months. This is according to a recent statement made by India’s Minister of Power. The 11.5 MW…

Waste to Energy
Chennai approves WtE project under PPP

Chennai approves WtE project under PPP

The Greater Chennai Corporation (GCC), Tamil Nadu, has approved a project to build a WtE plant under a PPP model. The plant is to process wet waste and RDF generated in processing plants in Kodungaiyur…

Waste to Energy
JBIC to provide loan for Bidadi Waste to Enery plant

JBIC to provide loan for Bidadi Waste to Enery plant

State-owned company Power Finance Corporation (PFC) has signed an agreement with the Japan Bank for International Cooperation (JBIC) on a JPY 1.85 billion (EUR 11.6 million) loan. The loan is to be used to finance…

Waste to Energy
New white paper on India’s Waste to Energy potential

New white paper on India’s Waste to Energy potential

As stated in a recent white paper, India can use its current waste volumes to produce 65 GW of electricity per year – and this can grow to 165 GW by 2030 and 436 GW…

Waste to Energy
New Bandhwari WtE plant to start in December 2024

New Bandhwari WtE plant to start in December 2024

According to the source, the WtE plant by EcoGreen Energy in Bandhwari, Gurugram, is facing further delays. The plant is now expected to be operational by December 2024. Construction at the plant begun in December…

Waste to Energy
Bidadi WtE plant to be operational in October

Bidadi WtE plant to be operational in October

The WtE plant in Bidadi, Karnataka, is now scheduled to start operations in October 2023. According to the source, civil works have been completed and the equipment is currently being assembled. The 11.5 MW plant…

Waste to Energy
New Waste to Energy facility to be inaugurated in Pune

New Waste to Energy facility to be inaugurated in Pune

Pimpri Chinchwad Municipal Corporation (PCMC) can now purchase electricity through open access from a Waste to Energy in Pune by Antony Lara Renewable Energy (ALREPL), without paying surcharges. The permit has been granted by the…

Waste to Energy
Dundigal’s new Waste to Energy plant about to open

Dundigal’s new Waste to Energy plant about to open

A 14.5 MW RDF incineration plant is about to open soon in Dundigal, Telangana. The facility has been set up at the Telangana State Industrial Infrastructure Corporation’s treatment, storage and disposal facility. As SWI understands,…

Waste to Energy
Update on new Kodungaiyur waste processing project

Update on new Kodungaiyur waste processing project

A new source provides more detailed information on the waste processing plants at the Kodungaiyur dump yard, planned by the Greater Chennai Corporation, according to The Hindu. The site is to include an MRF to…

Waste to Energy
Update on new Amritsar WtE project

Update on new Amritsar WtE project

The WtE project at the Bhagtanwala landfill in Amritsar, Punjab, is reportedly threatened by a property dispute and the omission of the Punjab State Power Corporation Limited (PSPCL) to issue a non-objection certificate (NOC) to…

Waste to Energy
Njeliyanparamba WtE project: biomining still not completed

Njeliyanparamba WtE project: biomining still not completed

On 30 April 2023, the grace period of 30 days for the completion of biomining and capping activities at the Njeliyanparamba WtE project in Kozhikode, Kerala, has reportedly ended. The deadline was issued by Kozhikode…

Waste to Energy
Jawaharnagar WtE facility to be expanded

Jawaharnagar WtE facility to be expanded

The Hyderabad State Minister for Municipal Administration & Urban Development has announced plans for an expansion of the Waste to Energy plant in Jawaharnagar, Hyderabad. The plant’s capacity is reportedly expected to increase from currently…

Waste to Energy
Update on Daighar Waste to Energy project

Update on Daighar Waste to Energy project

The Waste to Energy project in Daighar, Thane City, Maharashtra, is expected to begin its first phase of operations in two to three months. The second phase is also expected to start in the coming…

News
Brahmapuram fire aftermath: Kerala HC and Govt swing into action

Brahmapuram fire aftermath: Kerala HC and Govt swing into action

The Kerala High Court has observed that all rules for solid waste management were violated at the Brahmapuram waste treatment plant in Kochi. It has ordered the Kochi Municipal Corporation to produce contract documents and…

Waste to Energy
Chandigarh accepted recommendations for MSW plant

Chandigarh accepted recommendations for MSW plant

The Municipal Corporation of Chandigarh has accepted recommendations to convert dry waste into RDF and wet waste into biomethane and compressed natural gas at its proposed 600 tpd integrated waste management facility. Tender to be…

Waste to Energy
Meeting to be held on Brahmapuram WtE project

Meeting to be held on Brahmapuram WtE project

The WtE project in Brahmapuram, Ernakulam district, Kerala, is still under discussion. According to the source, the Kochi Corporation has announced that an all-party meeting on this long-standing project will be held soon. According to…

Waste to Energy
Delhi submits status report on WtE and waste management to the NGT

Delhi submits status report on WtE and waste management to the NGT

Delhi government has recently submitted a status report to the National Green Tribunal (NGT). As per the report, Delhi generated 11,332 tpd of MSW on an average. As further stated, there are currently four WtE…

Waste to Energy
Narela-Bawana Waste to Energy plant to increase capacity

Narela-Bawana Waste to Energy plant to increase capacity

Public consultations have been launched for the planned capacity increase at the Narela-Bawana WtE plant in Delhi. Plans provide to increase the plant’s capacity from 24 MW to 60 MW. At 24 MW, the plant…

Waste to Energy
Galand WtE facility will not start before July 2024

Galand WtE facility will not start before July 2024

The Ghaziabad Municipal Corporation (GMC) is planning to transfer 44.2 acres of land for a WtE plant in Galand village in Ghaziabad, Uttar Pradesh, to Dutch plant developer GC International. The developer urged the GMC…

Waste to Energy
5 Waste to Energy plants for Hyderabad

5 Waste to Energy plants for Hyderabad

The Greater Hyderabad Municipal Corporation (GHMC), reportedly plans to set up or revamp five Waste-to-Energy plants across Hyderabad. A 14.5 MW plant currently being constructed in Dundigal is to be commissioned by March 2023. The…

Waste to Energy
New Waste to Energy plant being set up at Deonar landfill

New Waste to Energy plant being set up at Deonar landfill

A WtE plant is currently being set up at the Deonar landfill in Mumbai, Maharashtra. As further reported, the 360 tpd facility is being set up by Waste Management Ltd, a wholly-owned subsidiary of Re…

Waste to Energy
New WtE facility proposed for Rajahmundry

New WtE facility proposed for Rajahmundry

A new WtE plant is being proposed in Rajahmundry, Andhra Pradesh. This was stated by the chief minister of Andhra Pradesh during a recent review meeting on the Municipal Administration and Urban Development in Amaravati,…

Waste to Energy
Shimla WtE plant to start electricity production

Shimla WtE plant to start electricity production

The Shimla WtE facility, Himachal Pradesh, has finally started energy production from waste. It has been operational for almost four years now. The plant has been developed by Australian company Elephant Energy in PPP mode…

Waste to Energy
Sheeshambada RDF project against NGT guidelines

Sheeshambada RDF project against NGT guidelines

The proposed RDF project in Sheeshambada in Dehradun, Uttarakhand, is reportedly inconsistent with the guidelines of the National Green Tribunal (NGT). As further stated in the source, plant developer RE Sustainability (RE), former Ramky Enviro,…

News
Tehkhand WtE plant inaugurated by Home Minister

Tehkhand WtE plant inaugurated by Home Minister

The large-scale Tehkhand WtE project in South Delhi has been inaugurated by the Union Home Minister on 20 October 2022. The 2,000 tpd facility in the Delhi district of Tughlakabad is supposed to generate up…

Waste to Energy
Okhla WtE expansion approved by NGT

Okhla WtE expansion approved by NGT

The National Green Tribunal (NGT) has approved the expansion of the Okhla Waste to Energy plant, Delhi, after the Expert Appraisal Committee (EAC) has refused the proposal in September 2022. Operator Okhla Waste Management Company…

Waste to Energy
Waste to Energy project in Vadodara delayed

Waste to Energy project in Vadodara delayed

The implementation of a Waste to Energy plant in Vadodara Municipality, Gujarat is delayed. As the source indicates, the plant by Abelan Clean Energy Ltd. should have been operational by December 2021. Furthermore, Abelan Clean…

Waste to Energy
New large-scale WtE plant proposed in Narela-Bawana

New large-scale WtE plant proposed in Narela-Bawana

The proposed new WtE facility to be built at Narela-Bawana, Delhi, is currently expected to be completed by August 2025. According to the Delhi Pollution Control Committee (DPCC), the Municipal Corporation Of Delhi (MCD) has…

Company news
CNIM Martin announces take over by Paprec Engineering

CNIM Martin announces take over by Paprec Engineering

Chennai-based CNIM MARTIN Private Limited (CMPL) has announced the finalization of its takeover by Paprec Group, via its holding company Paprec Energies International, of the 51% of its shares that were held by CNIM Environment…

Waste to Energy
Goa seeks funding from the Centre for Verna WtE project

Goa seeks funding from the Centre for Verna WtE project

The Goa state government is seeking funding from the Government of India for the WtE project by Goa Waste Management Corporation (GMWC). Reportedly, Goa is seeking INR 1.5 billion (EUR 18.82 million) from the Centre…

Waste to Energy
New WtE project could be built in Nashik

New WtE project could be built in Nashik

A new WtE plant could be built in Nashik, Maharashtra, as The Times of India reports. On 23 September 2022, Nashik Municipal Corporation held talks with Mahatma Phule Energy and Infrastructure Technology Ltd (MahaPreit), a…

Waste to Energy
Second WtE plant in Jawaharnagar nears commissioning

Second WtE plant in Jawaharnagar nears commissioning

The second WtE facility in Jawaharnagar, Telangana, is “almost ready for commissioning”. The project is planned to have a power supply capacity of 28 MWe, as Telangana Today reports. The first WtE plant in Jawaharnagar…

Waste to Energy
GMWC to set up new WtE plant in Verna

GMWC to set up new WtE plant in Verna

According to the Goa Waste Management Corporation (GMWC), plans provide to develop a new WtE plant in Verna, which is a village in Salcete, Goa. The plant should be set up in Verna at an…

Waste to Energy
Bandhwari WtE plant remains under development

Bandhwari WtE plant remains under development

According to a recent report on the WtE project in Bandhwari, Haryana, the facility has not yet been completed. An update from March 2022 stated that the 15 MW plant is scheduled to become operational…

Waste to Energy
Plans for new WtE plant in Srinagar City

Plans for new WtE plant in Srinagar City

There are plans for the development of a WtE plant in Srinagar City, Jammu and Kashmir. Srinagar Municipal Corporation (SMC) already completed “some documentation” for this project. Moreover, a PPA is expected to be completed…